EDGPA performed the following for the plant header replacement:

  • Replacement of the inlet / outlet headers to 11 heaters in Onshore treating system
  • Includes 24”, 18” and 12” header piping and 22 – 12” downcommers to heaters
  • Concrete foundations for new pipe rack
  • Structural steel design for new pipe rack
  • Significant challenge to locate new rack and piping adjacent to existing heaters