Substation Upgrade Transformer company

EDG’s substation transformer upgrade scope of work included: 
  • Replacing existing 10MVA T1 transformer with 33MVA 69 kV./13.8 kV. unit with LTC
  • Adding 1,200A feeder breaker
  • Re-conducting and constructing approximately 1.9 miles of distribution line utilizing 795 Al