WORKPAX Operating Procedures    

WORKPAX Operating Procedures

Structured project management and tracking

WorkPax is a centralized resource that offers a host of benefits for clients, construction management and construction teams in the planning, scheduling, implementing and progress tracking of projects, large and small.

Using engineering drawings and documents, WorkPax serves to define individual work tasks while providing a framework for construction sequencing through the use of a Critical Path Matrix. This matrix provides the basis for construction scheduling while enabling the user to generate accurate resource loading.

As an individual entity, WorkPax provides all the information and documentation required to accomplish a single construction task through the application of:

  • Specifically highlighted and annotated engineering drawings and documents for both demolition and installation (P&IDs, piping plans, lighting plans, structural renderings, cable schedules, instrument data sheets, specialty item lists, etc.)
  • Work permit identification
  • Task predecessors
  • A procedural outline of the work
  • Materials lists
  • Lockout/tagout referenced items
  • JSAs
  • Annotated photographs

   