Relocate Substation Control Room, EDG Relocate Substation

EDG’s project’s scope of work to relocate substation control room included: 
  • Installing pre-fabricated control house to accommodate accelerated schedule (complete with all relays and communications terminated to marshalling rack)
  • Pulling cables from new control house to instrumentation
  • Contracting local distribution co-op to provide station service while SSVT (Station Service Voltage Transformer) arrives
  • Adding fencing and limestone to complete separation of switchyard from former power plant