Client: BP Amoco Exploration
Location: Matagorda Island Block 519 "L" -
Gulf of Mexico
Project description: EDG provided engineering and drafting services to assist BP Amoco enhance an existing production facility for increased production. The new design doubled the facilities capacity to 180 MMSCFD of natural gas and provided space for future LP production and compression. A successful economic design required incorporation of three (3) existing high pressure production skids, a fuel gas skid, and refurbishing an existing meter skid. Project goals achieved included 100% shop spooling of ICP, installation of pipe hangers during demolition, and partial installation of production equipment during preliminary production shut-ins.
|